CRITICAL TO OUR FUTURE
“A Clean Mine powering Clean Energy”
Ema Rare Earth Project
June 2026
Bankable Feasibility Study
Disclaimer
This presentation has been prepared by Brazilan Critical Minerals limited (company).
This important notice and disclaimer applies to this presentation and any information provided in relation to
or in connection with the information contained in it.
This presentation contains information in summary form. Some of the information is based on publicly
available sources, has not been independently verified or may not be complete. It should be read in
conjunction with the Company’s other continuous and periodic disclosure announcements lodged with
Australian Securities Exchange, which are available at www.asx.com.au.
This presentation contains forward-looking statements which involve a number of risks and uncertainties.
These statements reflect current expectations, intentions or strategies regarding the future and assumptions
based on currently available information. Should one or more of the risks or uncertainties materialize, or
should underlying assumptions prove incorrect, actual results may vary from the expectations, intentions
and strategies described in this presentation.
No representation or warranty is made as to the accuracy, completeness, reliability, fairness, or correctness
of the information contained in this presentation. To the maximum extent permitted by law, no person,
including the company and their related bodies corporate, officers, employees, and representatives
(including agents and advisors), accept any liability or responsibility for loss arising from the use of such
information. This presentation is not a bidder’s statement, prospectus or a product disclosure statement
under the Corporations Act 2001 (Cth) or offering document under any other law. It has not been lodged with
the Australian Securities and Investments Commission.
This presentation is for information purposes only and is not financial product or investment advice or
intended to be used as a basis for making an investment decision. It has been prepared without taking into
account the investment objectives, financial circumstances, taxation position or particular needs of
investors.
This presentation does not constitute an offer to issue or sell, or to arrange to sell, securities or other financial
products. In particular, this presentation and the information contained in it does not constitute a solicitation,
offer or invitation to buy, subscribe for or sell any security in the United States or to or for the account or
benefit of any U.S. Person (as defined in Regulation S under the U.S. Securities Act of 1933, as amended (the
US Securities Act)). The securities referred to in this presentation as being offered or sold have not been, and
will not be, registered under the US Securities Act. Securities may not be offered or sold in the United States
unless they have been registered under the US Securities Act or an exemption from registration is available.
The release, publication or distribution of this presentation in jurisdictions outside Australia may be restricted
by law. Any failure to comply with such restrictions may constitute a violation of applicable securities laws.
Competent person statement
The information in this report that relates to exploration results is based on information
compiled by Mr. Antonio de Castro, BSc (Hons), MAusIMM, CREA, who acts as BCM´s Senior
Consulting Geologist through the consultancy firm, ADC Geologia Ltda. Mr. de Castro has
sufficient experience which is relevant to the type of deposit under consideration and to the
reporting of exploration results and analytical and metallurgical test work to qualify as a
competent person as defined in the 2012 Edition of the Joint Ore Reserves Committee (JORC)
“Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”.
Mr. Castro consents to the report being issued in the form and context in which it appears.
The information in this report that relates to exploration results is based on information
compiled by Mr. Antonio de Castro, BSc (Hons), MAusIMM, CREA, who acts as BCM´s Senior
Consulting Geologist through the consultancy firm, ADC Geologia Ltda. Mr. de Castro has
sufficient experience which is relevant to the type of deposit under consideration and to the
reporting of exploration results and analytical and metallurgical test work to qualify as a
competent person as defined in the 2012 Edition of the Joint Ore Reserves Committee (JORC)
“Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”.
Mr. Castro consents to the report being issued in the form and context in which it appears.
The Company confirms that it is not aware of any new information or data that materially
affects the information included in the relevant market announcement and, in the case of
mineral resource estimate, that all material assumptions and technical parameters
underpinning the estimates in the relevant market announcement continue to apply and
have not materially changed. Refer to ASX announcement dated 01 July 2025.
Exploration results and mineral resources
The information in this announcement relates to previously reported exploration results and
mineral resource estimates for the Ema Project released by the Company to ASX on 22 May
2023, 17 July 2023, 19 July 2023, 31 July 2023, 13 Sep 2023, 19 Oct 2023, 06 Dec 2023, 06 Feb 2024,
22 Feb 2024, 13 Mar 2024, 02 Apr 2024, 08 Oct 2024 19 Nov 2024, 21 Jan 2025, 17th Feb 2025,
26th Feb 2025, 10th March 2025, 13th March 2025, 28th April 2025, 27th May 2025, 28th May, 13
June 2025, 01 July 2025, 18 August 2025, 01 Sep 2025, 22 Sep 2025 and 23 Oct 2025, 1 Dec 2025,
17 Dec 2025, 12 Jan 2026 and 03 Mar 2026. The Company confirms that is not aware of any
new information or data that materially affects the information included in the above-
mentioned releases and CONTINUES TO APPLY and have not materially changed in
accordance with listing Rule 5.23.2. This presentation has been approved by the Board
of Directors.
BFS Highlights
EMA Rare Earth Project
Superior Return
on Investment
US $1.47B
Post-tax NPV
Strong Capital
Efficiency
IRR 105%
Post-tax IRR
Scalable Asset
Potential
US $152M
Post-tax free
Operating Cashflow
Western Worlds
Lowest
US $74M
Capex to Stage 1
Production
Lowest Quartile
Cost Curve
US $8.84/kg
Opex Costs per kg
TREO (AISC)
Rapid Payback
Period
0.5 years
Post-tax
Common
extraction
technique
300-400
Operating ISR
Mines
Payability
Estimate
70%
High Composition
of NdPr
Mineral
Resource
1.07 Bt
Multi-Generational
Mine Life
Annual Production
(LOM avg)
10,500t MREC
5,500t TREO
1,900t MREO
Pre-production Capital
US$74.0M
includes 14.4% contingency
Mine Life
20 years
Cash Costs (C1)
US$8.84/kg TREO
US$22.44/kg MREO
Free Cash Flow (post-tax
Base Case Pricing)
US$3,369M
Free Cash Flow (post-tax
High Case Pricing)
US$4,239M
Free Cash Flow pa (post-
tax Base Case Pricing)
US$152M
NPV8 (post-tax Base Case)
US$1,466M
NPV8 (post-tax High Case)
US$1,856M
IRR (Base Case)
105%
IRR (High Case)
124%
Payback Period – Base
Case
~0.5 years
Brazilian Critical Minerals (ASX:BCM) : Ema BFS Delivers Exceptional Economics 30th June 2026
Low-Cost, High-Return
Long-Life, Quick Return
Key Financial Measures
Cashflow & Earnings
Metrics
Unit
Base
Case
High
Case
Annual Revenue US$M 265 318
Revenue (gross) US$M 5,436 6,526
Annual EBITDA US$M 219 271
Annual Operating Costs US$M 42 42
Annual Operating Costs US$/kg TREO 8.84 8.84
Annual AISC (inc. royalites) US$/kg TREO 13.02 13.02
Operating Annual Cashflow
(post-tax) US$M 152 192
Project net cashflow
(post-tax)
US$M 3,353 4,220
NPV, returns and key metrics Unit
Base
Case
High
Case
NPV8% (post-tax, ungeared) US$M 1,466 1,856
IRR (post-tax, nominal basis) % 105 124
Payback period (post-tax, from first
production) Years 0.5 0.3
Capital efficiency (pre-tax NPV /
capex) x 16 x 21 x
Rare Earth Pricing (LOM) Unit
Base
Case
High
Case
R$/US$ (long term forecast) USr 5.15 5.15
NdPr price forecast US$/kg 108 130
Dy price forecast US$/kg 1,583 1,900
Tb price forecast US$/kg 3,869 4,643
Ema Capable of Generating
Significant Shareholder Returns
Under Current Pricing
20 year plan – 2 processing plants
• Ability to recycle lixiviant
between operating
wellfield pods
• Long-life resource with
substantial potential for
future expansion
• Strong Tier-1 economics
combined with exceptional
ESG credentials
Capital and Operating Costs
Capital Requirements Unit Base Case
Pre-production capital (Stage 1) US$M 74
LOM sustaining capital expenditure US$ / year 12.95
Unit cash operating costs (Avg LOM) Unit Base Case
Annual operating cost US$M 42.4
Annual operating cost US$/kg TREO 8.84
Annual AISC US$/kg TREO 13.02
Capex of US$74M inclusive of
• US$19M carbon capture storage
• 14.4% contingency
Capital Efficiency (Stage 1 & 2)
• 16x pre-tax NPV
Stage 2 Expansion
• Capex US$27M
• 100% expansion of Stage 1
Brazilian Critical Minerals (ASX:BCM) : Ema BFS Delivers Exceptional Economics 30th June 2026
CAPEX US$M
%
of total
Direct Costs
Mechanical 28.84 39%
Piping 6.85 9%
Structural 6.99 9%
Engineering 3.60 5%
Other 20.30 28%
Indirect Costs
Mob – Plant & People 0.97 1%
Site Establishment 1.30 2%
Off-Site Management 1.89 3%
Site Support 0.92 1%
Other 2.04 3%
Total 73.71 100%
Capex Cost
• Large cost centres are well field setup
and plant earthworks
• US$12.5M in Wellfield 1 development
costs (Year 1 production only)
• CCS US$19M (Stage 1 & 2 requirements)
• Lowest Capex of any rare earth project
in development producing an MREC
Base Pricing - US$108*/kg NdPr avg
High Pricing – US$130*/kg NdPr avg
US$74M Capex – 0.5 year Payback
Base Price NPV – US$1,466M (post-tax)
High Price NPV – US$1,856M (post-tax)
*Average LOM values
US$3.4B
US$4.2B
LOM Production
Cashflow & Earnings Metrics Unit BFS Scoping
In-situ TREO Grade Leached ppm 732 743
MREO Recovery % 55 62
Average Annual Production t MREO 38,020 36,252
Total Production t REO 109,500 95,651
Total Production t MREC 210,500 173,000
Average Annual Production t MREO 1,900 1,813
Project net cashflow (post-tax) US$M 3,369 911
Brazilian Critical Minerals (ASX:BCM) : Ema BFS Delivers Exceptional Economics 30th June 2026
A New Standard for Low-Impact
Mining
Exceptional ESG credentials
• Low greenhouse gas emissions
• Minimal surface disturbance
• No conventional mining or open pits
• No waste-rock dumps
• No tailings storage facility
• Minimal noise and dust
Operating Costs (Stage 1)
• Reagents + Power 67% of Opex costs
• Generator based site power (pumping + CO2 capture)
• Magnesium Sulphate sourcing Brazil and ex-Brazil
Operating Costs
(Real LOM)
ANNUAL COST
PRODUCTION
BASIS
DISTRIBUTION
US$M/A $/kg TREO %
Fixed Costs
Labour 3.13 0.98 15%
Miscellaneous 0.61 0.19 3%
Maintenance 1.76 0.55 9%
G & A 1.05 0.33 5%
Subtotal 6.55 2.06 32%
Variable Costs
Reagents 6.79 2.13 34%
Logistics & Disposal 0.03 0.01 0%
Electrical Power 6.58 2.07 33%
Consumables 0.30 0.09 1%
Subtotal 13.70 4.30 68%
TOTAL BASE CASE 20.25 6.35 100%
Labour
15%
Miscellaneous
3%
Maintenance
9%
G & A
5%
Reagents
34%
Logistics &
Disposal
0%
Electrical Power
33%
Consumables
1%
Annual operating cost by Category
Operating costs are presented on a single Stage 1 process plant above. LOM unit cash operating costs
(C1) of US$8.84/kg TREO reported in Table 3 of the BFS Report are calculated on total site operating
costs across Stage 1 & 2, divided by LOM average TREO of 5,500 tonnes per annum, inclusive of ramp-
up periods.
AISC by Category
67.5% reduction in the Corporate Income
Tax lowering the rate from 25.0% to 8.13%
Brazilian Critical Minerals (ASX:BCM) : Ema BFS Delivers Exceptional Economics 30th June 2026
$-
$50
$100
$150
$200
$250
$300
$350
$-
$50
$100
$150
$200
$250
$300
$350
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Gross
Revenue
US$M
AISC
Cost
by
Category
US$M
Operating Cost Depreciation Royalties Revenue
LOM Price NdPr
• US$108/kg
Low All in Sustaining Cost
• US$13.02/kg TREO
• US$37.50/kg MREO
High Margins and
Profitability
High NPV post tax
Study Pricing Scenarios
CIF North America
Benchmark Mineral Intelligence Ltd: Base Case CIF North America NdPr Oxide Price 99.5%, Dy2O3 99.99%, Tb2O5 99.99% US$ Real June 2026
All other REE elements based on ExW-China prices
Historical Prices: Open Source, adjusted for inflation
0
40
80
120
160
200
240
US$/kg
NdPr
oxide
Historical Prices Base Case High Case Low Case
Pricing
LOM Avg
Rare Earth Oxide Pricing (US$/kg)
NdPr Ox Dy2O3 Tb2O5
*TREO
Basket
High Case 130 1,899 4,643 61
Base Case 108 1,583 3,869 51
Low Case 86 1,266 3,095 41
*Bakset price inclusive of payabilities
Price Sensitivities
Pricing
LOM Avg
Rare Earth Oxide
Pricing (US$/kg)
Post Tax NPV Post Tax IRR
NdPr Ox (US$m) (%)
High Case 130 1,855 124%
Base Case 108 1,465 105%
Low Case 86 1,075 84%
Benchmark Mineral Intelligence Ltd: Base Case CIF North America NdPr Oxide Price 99.5%, Dy2O3 99.99%, Tb2O5 99.99% US$ Real June 2026
Historical Prices: Open Source, adjusted for inflation
*TREO Basket: Based on prices NdPr Oxide Price 99.5%, Dy2O3 99.99%, Tb2O5 99.99% only. Zero payability attributed to all remaining oxides.
Sensitivty to NdPr oxide price
POST-TAX
NPV (US$ M)
-30% -20% -10% 0% 10% 20% 30%
DyTb Price 1,168 1,267 1,366 1,465 1,564 1,663 1,762
NdPr Price 1,175 1,272 1,369 1,465 1,562 1,659 1,756
MgSO4 1,484 1,478 1,472 1,465 1,459 1,453 1,447
Recovery 1,283 1,405 1,461 1,465 1,468 1,473 1,478
CAPEX 1,485 1,478 1,472 1,465 1,459 1,452 1,446
BFS vs Scoping
Unit Scoping BFS
Date Feb 2025 June 2026
Project Ema Ema
Mine Life years 20 20
Capex US$M 55 74
NPV (pre-tax) US$M 668 1,785
IRR (pre-tax) % 63 120
Price Forecast – Base Case US$/kg (NdPr) 60 108
NPV (post-tax) US$M 355 1,465
IRR (post-tax) % 52 105
Inclusive Capex Contingency % 35 14
Operating Cost (LOM) US$/kg TREO 6.15 8.84
Operating Cost (LOM) US$/kg MREO 16.24 22.44
Payability % 70 70
Capex - US$74M
• 4 x increase in post-tax NPV
• 102% increase in IRR
• Capital effiency 16x (Stage 1
and 2) pre-tax NPV
Cost Curve Analysis
0
5,000
10,000
15,000
20,000
25,000
30,000
BCM
Ema Project
Other Ionic Clay
Projects
China Ionic Clays
Lynas Mt Weld
MP Materials
Mountain Pass
Bayan Obo
t REO
BCM Ema Project (ISR) Rest of World Projects and Operations
US$/tonne
REO
Source: Company reports, Public filings
190
Large Resource Base
732
TREO ppm
392M
Indicated Tonnes Mt
Global Mineral Resource Estimate – April 2026
37% Indicated Resource
JORC
Category
cut-off
ppm
TREO
Tonnes
Mt
TREO
ppm
NdPr
ppm
DyTb
ppm
MREO
ppm
MREO:TREO
%
Indicated 500 392 773 184 17 200 25
Inferred 500 681 712 168 15 184 25
*Total 500 1,071 732 174 16 190 25
Ema REE Project 2026 Mineral Resource Estimate
25%
MREO:TREO NdPr + DyTb ppm
Global MRE 943Mt is inclusive of Central Starter Zone total of 341Mt
In-Situ (REE) Leaching
most common form of REE extraction
• Low establishment cost
• Proven decades old
technology
• Using gravity as our
natural pumping system
• Readily leachable solution
laden with rare earths
• ISR accelerates natural
processes in the ground
In-Situ Leaching involves just three steps:
• Inject a lixiviant (magnesium sulfate)
• Dissolve or desorb the REE elements into solution using Mg ions
• Pump the pregnant solution back for processing
Liquid Collection Zone
Leaching Injection Well
Bedrock Clay Zone Leaching Solution
To Plant
Extraction
Wells
$50.75
Basket composition and price
Scoping Pricing: https://giti.sg/markets/markets_files/89cdfc0a3db0583ce2caf7f5d3feec97-212.html
BFS Pricing: Commissioned pricing from Benchmark Intelligence Ltd – June 2026
>95%
Magnet value in Basket
Value of Payability Basket per kg – Base Price assumption
>34.5%
MREO:TREO – strong DyTb
composition for Ionic Clay
Strong Basket Price – right elements
MREC BASKET PRICE
BFS Scoping
June 2026 Feb 2025
Oxide US$/kg % Basket $ US$/kg % Basket $
La2O3 29.52 0.53 34.7 0.18
CeO2 16.47 1.14 8.9 0.10
NdPr (99.5%) 108 32.61 35.4 62 36.3 22.33
Sm2O3 3.99 2.09 4.6 0.10
Eu2O3 0.45 27.19 0.5 0.14
Gd2O3 2.56 23.15 2.9 0.67
Tb4O7 (99.9%) 3,869 0.29 11.06 859 0.3 2.33
Dy2O3 (99.5%) 1,583 1.65 26.09 243 1.4 3.33
Ho2O3 0.28 66.24 0.2 0.16
Er2O3 0.84 41.14 0.7 0.29
Tm2O3 0.10 112.4 0.1 0.11
Yb2O3 0.63 14.08 0.6 0.08
Lu2O3 0.06 718.2 0.1 0.61
Y2O3 10.55 5.72 8.7 0.50
Basket Price US$/kg (TREO) 30.94
Basket Price US$/kg (NdPrDyTb) 72.49 27.99
Potential payability (70%) 50.75 19.6