EMA FIELD TRIAL COMMENCES
Highlights
•
In-situ recovery (ISR) mining trial injecting magnesium sulphate into shallow clay horizon has
commenced at the Ema Project
•
Pilot trial is being conducted by global industry ISR leader WSP Brazil and overseen by CERN
environmental following successful trials conducted at ANSTO recently1
•
ISR field test program is designed to validate various deposit-specific characteristics of Ema, and
to collect a database of geotechnical, hydrogeological, and metallurgical data to evaluate the
deposit conditions, and optimise the proposed ISR mining of Ema
•
Previous ANSTO testwork suggests the soft, friable, quartz rich nature of Ema mineralisation
results in high recoveries of key magnet rare earth elements over short leaching duration
periods, driving highly favourable operating costs
•
ISR trial is expected to take up to three months to complete multiple scenarios and includes
water washing and clay rehabilitation testwork
Andrew Reid, Managing Director, commented:
“24 months ago, we discovered the Ema deposit, 12 months ago we released a maiden 1Bt MRE, 3
months ago we delivered an ultra-low CAPEX/OPEX Scoping Study after extensive metallurgical
testing.
Today we have commenced in-situ trials with the planned objectives to provide validation that the
Ema deposit possesses the characteristics necessary for a full scale commercial ISR operation.
This trial is a further step advancing on the existing testwork completed within Brazil and ANSTO which
underpinned the Scoping Study delivering a project NPV of US$355M (even at current depressed spot
prices), with a project capital requirement of just US$55M.
The data collected will confirm hydraulic conductivity, demonstrate the clay permeability and allow
us to collect metallurgical samples for further leach optimisation work planned.
On the back of the expected positive results, the Company plans to produce a Mixed Rare Earth
Carbonate (MREC) from the collected solution. This MREC will then be provided to strategic partners
for quality control testing and to progress the execution of offtake agreements."
Brazilian Critical Minerals Ltd (ABN: 82 089 221 634)
AUS: Level 28, 140 St Georges Terrace, Perth WA 6000 T +61 8 6383 7820
BRA: Av Jornalista Riccardo Marinho, 360, Sala 113, Barra da Tijuca, Rio de Janeiro T +55 21 2439 57
ASX Announcement
Released 14th May 2025
https://braziliancriticalminerals.com/
Investor Hub: https://braziliancriticalminerals.com/auth/signup
Brazilian Critical Minerals Limited (ASX: BCM) (“BCM” or the “Company”) is pleased to announce that
in-situ recovery field trials have commenced at the Ema Rare Earths Project in Brazil. This trial will enable
the Company to assess the hydrogeological conditions, obtain valuable information on the leach
characteristics of the rare earths, whilst collecting solutions rich in rare earths able to generate a final
mixed rare earth carbonate product.
ISR is mainly suitable for ion-adsorption clays (e.g., in southern China, Malaysia and parts of Myanmar)
with limited commercial-scale projects outside China, with the exception of Ema. The Ema project has
such unique geological characteristics achieving high recoveries utilising an environmentally responsible
reagent, magnesium sulphate, with the lowest capital intensity requirement of any western rare earth
project.
Figure 1. view of the water storage and magnesium sulphate storage tanks piped to injection holes
designed and drilled to optimise and test solution permeability.
Key Objectives of the trial include the following:
•
Confirm Hydraulic Conductivity: Pump and injection tests to validate hydraulic connectivity of
the test injection holes within the mineralized zone. Determining that there is sufficient
permeability within the mineralised zone is a key criterion for the successful deployment of the
ISR mining method.
•
Demonstrated Effective Permeability: Demonstrate the suitability of the ISR method to the
Ema deposit. Validate the conditions required to effectively permeate lixiviant and leach rare
earths into solution for further downstream recovery.
•
Collect Metallurgical Samples for Leaching Characteristics: Extract leached solutions within the
trial area from the collection holes rich in rare earths so as to conduct impurity removal and
precipitation tests to produce the final product, a mixed rare earth carbonate.
Brazilian Critical Minerals Ltd (ABN: 82 089 221 634)
AUS: Level 28, 140 St Georges Terrace, Perth WA 6000 T +61 8 6383 7820
BRA: Av Jornalista Riccardo Marinho, 360, Sala 113, Barra da Tijuca, Rio de Janeiro T +55 21 2439 57
ASX Announcement
Released 14th May 2025
https://braziliancriticalminerals.com/
Investor Hub: https://braziliancriticalminerals.com/auth/signup
The trial includes the setup of various pump, injection, and trials designed to assess the permeability of
the Ema deposit.
The test program will measure solution volumes and pressures of the magnesium sulphate lixiviant
pumped into the holes which provides evidence of the deposit's hydraulic conditions and is indicative of
the movement of solution in an ISR mining operation.
References
1
Brazilian Critical Minerals (ASX:BCM) – Ema Field Permeability Testing Successful 20th August 2024
2
Brazilian Critical Minerals (ASX:BCM) – Massive Maiden Mineral Resource for Ema Project 22nd April
2024
This announcement has been authorised for release by the Board of Directors.
Enquiries
For more information please contact:
Andrew Reid
Managing Director
Brazilian Critical Minerals Limited
Andrew.reid@braziliancriticalminerals.com
Brazilian Critical Minerals Ltd (ABN: 82 089 221 634)
AUS: Level 28, 140 St Georges Terrace, Perth WA 6000 T +61 8 6383 7820
BRA: Av Jornalista Riccardo Marinho, 360, Sala 113, Barra da Tijuca, Rio de Janeiro T +55 21 2439 57
ASX Announcement
Released 14th May 2025
https://braziliancriticalminerals.com/
Investor Hub: https://braziliancriticalminerals.com/auth/signup
Brazilian Critical Minerals Limited (BCM) is a mineral
exploration company listed on the Australian
Securities Exchange.
Its major exploration focus is Brazil, in the Apuí
region, where BCM has discovered a world class Ionic
Adsorbed Clay (IAC) Rare Earth Elements deposit. The
Ema IAC project is contained within the 781 km² of
exploration tenements within the Colider Group and
adjacent sediments.
BCM has defined an indicated and inferred MRE of
943Mt of REE’s with metallurgical recoveries
averaging 68% MREO, representing some of the
highest for these types of deposits anywhere in the
world.
The Company has converted the MRE central portion
from Inferred into the Indicated category with an
extensive drill program during 2024 which has
underpinned the scoping study and economic
analysis released in February 2025.
Ema REE Global Mineral Resource Estimate @COG 500ppm TREO
JORC
cut-off
Tonnes
TREO
NdPr
Category
ppm TREO
Mt
ppm
ppm
Indicated
500
248
759
176
Inferred
500
695
701
165
Total
500
943
716
168
DyTb
ppm
16
16
16
MREO
ppm
192
181
184
MREO: TREO
%
25
26
26
The information in this announcement relates to previously reported exploration results and mineral
resource estimates for the Ema Project released by the Company to ASX on 22 May 2023, 17 July 2023,
19 July 2023, 31 July 2023, 13 Sep 2023, 19 Oct 2023, 06 Dec 2023, 06 Feb 2024, 22 Feb 2024, 13 Mar
2024, 02 Apr 2024, 08 Oct 2024 19 Nov 2024, 21 Jan 2025, 17th Feb 2025, 26th Feb 2025, 10th March
2025, 13th March 2025 and 28th April 2025. The Company confirms that is not aware of any new
information or data that materially affects the information included in the above-mentioned releases.
Brazilian Critical Minerals Ltd (ABN: 82 089 221 634)
AUS: Level 28, 140 St Georges Terrace, Perth WA 6000 T +61 8 6383 7820
BRA: Av Jornalista Riccardo Marinho, 360, Sala 113, Barra da Tijuca, Rio de Janeiro T +55 21 2439 57
Share your feedback
Discover